Daniel Burke, Mike D, Sven, Scott A, Joel, Jem, Anthony Cala, Benoit, Dave V, Eric D'Ercole (PgM for FN)
3 devices available total for the duration
USB tethering working (Jabil) and 2 weeks from today March 4
ICD update is coming in the next week but will be minor update. Spelling formatting etc.
DB not a fan of the way we are handling the blockers.
Doesn't feel current approach is working.
DB is asking for blockers to be written at a highly technical level and delivered to the technical leads at Jabil.
The issues need to be outlined in a more technical manner so they can be addressed as such.
Mike D / Sven said that we are already doing that and holding technical meetings.
DB says yes but we need more technical requests/documentation in our requests.
AC is saying that the details in the JIRA issues do not match requests to fix blockers sent to FN/Jabil.
Sven brought up the idea of having a smaller team. Benoit agrees that they are not able to keep up with the Unity team and a smaller team would be more manageable for FN/Jabil to keep up with.
BLUF - Jabil needs more technical details in order to take action on Unity requests
REQUEST FORMAT
What requirement are you trying to meet?
Priority of the issue.
What is the specific blocker?
What are the ripple effects of this blocker? Does it impact other issues?
Technical details necessary to reproduce/diagnose the issue. Technical Technical Technical
JIRA Fields
Impact field
Issue Risk
Description field
Tracability (to SOW)
Mitigation
Outcome/Solution